ISS Daily Summary Report – 9/09/2021

Russian Segment (RS) Extravehicular Activity (EVA) #50: Today, FE-4 Oleg Novitskiy (EV1) and FE-5 Petr Dubrov (EV2) egressed the Mini-Research Module (MRM)-2 airlock and completed the following tasks during today’s 7 hour and 25-minute EVA:

  • Mating of Ethernet cable from ISS USOS to MLM
  • Installation of gap spanner at ПГО-2 along MLM Pl. III
  • Mating MLM-SM interfaces:
    • Ethernet patch cable
    • two (2) HF cables between SM and MLM TV systems
    • cable between SM “KURS-P” antenna-feeder unit and MLM “KURS-P” antenna-feeder unit
  • Redirection of БКДО (Plume Impingement and Deposit Monitoring) unit
  • Installation of platform with adapters on MRM2 БТП-2 Passive Base Point
  • Deployment of installation platform with three BIORISK-MSK containers on MRM2
  • Installation of MLM ПГО-2 – ПГО-1 gap spanner (3ea.) (time permitting)
  • Taking photos of ISS RS exterior (time permitting)

United States On-orbit Segment (USOS) Astronaut FE-6 Mark Vande Hei aided the Russian crew in pre and post EVA operations. This is the second EVA that has focused on integrating MLM to the ISS.

Payloads

Four Bed Carbon Dioxide (CO2) Scrubber: The crew configured the Basic Expedite the Processing of Experiments to Space Station (EXPRESS) Rack-11 at LAB1P4 for Four Bed CO2 Scrubber installation. Four Bed CO2 Scrubber demonstrates a technology for removing CO2 from the atmosphere on a spacecraft. The technology is based on the current system in use on the ISS with mechanical upgrades in absorption beds, heater elements and valves, and the use of an improved zeolite absorbent to reduce erosion and dust formation. A goal for next-generation systems is continuous operation for 20,000 hours without a failure. This technology demo is a step toward that goal.

BioMole: A crewmember performed surface swab sampling of the ISS surfaces in order to identify bacteria by extraction of DNA using miniPCR16. The Environmental Health System (EHS) Biomole Facility non-culture based samples are capable of providing microbial identification on-orbit within days of sampling. The goal of this technology demo is to conduct comparative analysis for possible replacement of current microbial monitoring systems.

GRASP: A crewmember performed GRASP science protocols in the seated configuration. The purpose of the Gravitational References for Sensimotor Performance: Reaching and Grasping (GRASP) investigation is to better understand how the Central Nervous System (CNS) integrates information from different sensations (e.g. sight or hearing), encoded in different reference frames, in order to coordinate the hand with the visual environment. More specifically, the science team seeks to better understand if, and how, gravity acts as a reference frame for the control of reach-to-grasp.

The ISS Experience: A crewmember assembled and installed The ISS Experience EVA Z-Cam onto the JEM Airlock Slide Table. The ISS Experience is a cinematic Virtual Reality (VR) series documenting life and research aboard the space station. Filmed over multiple months, the immersive VR series documents different crew activities – from science conducted aboard the station to preparation for a spacewalk.

Systems

In-Flight Maintenance (IFM) Video Tape Recorder (VTR) Removal: The crew removed VTR-1 and VTR-2 from US Lab Bay 5 and prepared them for return on Cargo Dragon SpaceX-23 (SpX-23). VTRs have not been used since the Integrated Communications Unit (ICU) activation and were “abandoned in place” until crew time was available for their removal.

HMS Fundoscope Battery Maintenance: The crew charged the primary and backup battery pack for the on-board fundoscope. The fundoscope is used to perform regularly scheduled eye exams on-board station to monitor crewmembers eye health. Eyesight is one of the many aspects of the human body affected by long-duration stays in a microgravity environment. 

SpX-23 Cargo Transfer: Today, the crew performed SpX-23 cargo transfer operations and will continue to work cargo operations throughout the week.

Completed Task List Activities:

  • Extravehicular (EVA) Hardware (HDWR) Gather

Today’s Ground Activities:
All activities are complete unless otherwise noted.

  • RS EVA #50 Ground support
  • Atmosphere Revitalization System (ARS) Lab Major Constituent Analyzer (MCA) Zero Calibration
  • Video Distribution Subsystem (VDS) EVA configuration
  • Attitude Control System (ACS) Handover Attitude Control from USOS to RS for MRM2 Depress
  • Command and Data Handling (CDH) System Configuration prior to the External (EVA) Ops Mode Transition

Look Ahead Plan

Friday, September 10 (GMT 253)
Payloads:

  • APEX-08 Harvest (NASA)
  • CBEF Humidifier Closeout (JAXA)
  • Cell Science-04 LSG OBT (NASA)
  • CIR IPSU-G Drive Replace
  • Food Acceptability (NASA)
  • Food Physiology Diet Brief (NASA)
  • GRASP Free ops and HW stow(ESA)
  • LIDAL return 2 (NASA)
  • Plant Hab-04 Debris ops and H2O refill (NASA)
  • Redwire Regolith Print removal and stow (NASA)
  • Space Embryo Sample Fixation (JAXA)
  • Turbine Ceramic Module Install 1 (NASA)

Systems:

  • Dragon cargo ops
  • EVA Tool Transfer
  • EVA Tool Reconfiguration
  • EVA Helmet Light Install
  • Rechargeable EVA Battery Assembly (REBA) powered hardware checkout

Saturday, September 11 (GMT 254)
Payloads:

  • APEX-08 insert into ICEBERG (NASA)
  • LSG Work Volume Deploy (NASA)

Systems:

  • EVA Battery Operations Terminal (EBOT) procedure review
  • Equipment Lock (E-LK) Preparations
  • EVA Tool Configurations
  • EVA Tool Audit
  • EVA procedure review
  • EVA Procedure conference

Sunday, September 12 (GMT 255)
Payloads:

  • CS-04 Bioreactor Removal (NASA)
  • LSG Decontamination HW removal (NASA)

Systems:

  • USOS 4A ISS Roll-out Solar Arrays (IROSA) Prep EVA

Today’s Planned Activities:
All activities are complete unless otherwise noted.

  • BioMole Part 1: Surface Sampling and DNA Extraction
  • Health Maintenance System (HMS) Fundoscope Battery Maintenance Charge
  • JEM Airlock Slide Table (ST) Extension to JPM Side
  • ISS Experience EVA Z-Cam Installation to the JEM Airlock Slide Table
  • In-Flight Maintenance Video Tape Recorder (VTR-2) Removal
  • JEM Airlock Slide Table (ST) Retraction from JPM Side
  • In-Flight Maintenance Video Tape Recorder (VTR-1) Removal
  • BioMole Part 2: DNA Cleanup and Amplification
  • GRASP science performance in seated position
  • EXPRESS Rack 11B Locker Removal
  • Stowage Gather for LAB1P4 Basic Express Rack (BER) Outfitting for Four Bed CO2 Scrubber Installation
  • Urine Transfer System Offload EDV Swap
  • PRE-EVA airlock operations
  • Cargo Transfer to Dragon
  • Payloads Network Attached Storage (NAS) Vent Cleaning
  • LAB1P4 Basic Express Rack (BER) Prep for Four Bed CO2 Scrubber Installation
  • Regenerative Environmental Control and Life Support System (ECLSS) Recycle Tank Fill Part 3
  • EVA-50 Tasks
  • Extravehicular Mobility Unit (EMU) Long Life Battery (LLB) Installation
  • EVA Battery Operations Terminal Terminate
  • Bag Culture rewater
  • BioMole MELFI Insert
  • Post EVA Repress
  • RS ISS Reconfiguration for Nominal Ops